The three calls concerned separate proposed jobs. One caller needed a bid with additional items. Another planned to prepare the base before having asphalt placed. The third wanted faded accessible parking markings refreshed. Our discussion addressed a different question in each call.
The bid included work beyond the yard
The first caller had information to send for a basic bid. The requested bid included a lay down yard estimate and additional items, so the yard was not the full scope.
They just need kind of a basic bid there and I've got all the information I can send to you.
Okay, well, just like I said, send it in and I'll see what I can do.
We offered to review the information the caller sent. Our preference was also to visit the site. We explained that seeing the project helps us understand what is happening before preparing an estimate.
I mean, I do like to do on site, you know, you know, visiting.
The preparation discussion focused on the base
The second caller wanted to do the preparation and hire someone to place asphalt on top. Our discussion concerned the base for that work. The request was separate from the earlier bid call.
I think I want to do the prep work myself and just have somebody come in and do asphalt on top.
You got to make sure everything's, you know, right for foundation, I mean, what kind of base are you going to be using?
We asked what base material the caller planned to use. The caller said crushed rock. Our suggestion was good stabilized crushed rock, if possible, and we emphasized that a suitable base was important for the planned asphalt work.
When they want to go with crushed rock.
I would suggest a good stabilized crush rock, if possible.
The markings needed a refresh, not concrete repair
The third caller requested a refresh of faded accessible parking markings. The caller described fading and said there was no damage.
It's all faded, and I'm trying to get someone to come out here and kind of redo it for us.
Okay, is it concrete application or asphalt or.
We asked whether the surface was concrete or asphalt and whether the request involved a ramp. The caller identified concrete and repeated that it was not damaged.
No, it's not damaged.
Our later questions clarified that the work concerned the colored parking markings. We acknowledged the request as a painted-marking refresh. The caller defined that scope; we did not recommend concrete repair.
You need to freshen up.
Our takeaway is specific to each call: review the bid information, discuss the planned base, and separate faded markings from damaged concrete. The calls describe individual requests and our responses, not one project or a completed outcome.
You can discuss your bid scope, preparation plans, or faded parking markings with us.